Category Archives: Architecture

Progress Continues at Northcoast Behavioral Health Dietary Building

The project recently expanded to include replacement of the existing restroom fixtures and partitions, which everyone thought would look very dated when seen next to the renovated office area around it. After demolition was completed in the kitchen areas, work started on framing the new office walls for the new office suite. This included updating the existing window wall while retaining the existing wheelchair ramp, which provides accessible entry to restrooms for workers in the maintenance building in the rear. Construction is anticipated to be completed in Fall 2026.
      Left: Exterior windows and wall being updated. Right: Framing for new offices where the two windows are being updated.

All THAT Teen Center Construction Starts Up Again

After the roof replacement, construction at the All THAT Teen Center went on hold as discussions took place with the City building department on whether the project needed a site compliance plan review. Finally, the building department agreed that since there was an ownership change and not a use change (building was still leased by a church for Sunday services), a site compliance plan was not required. However, since the classrooms were used for after school activities and not Sunday school activities, the examiner required that each classroom have an individual smoke detector in addition to the fire alarm system and rated corridor doors already in the project. After the updated fire alarm plans were approved, construction could finally start on the last phase of the project, which is now scheduled to be completed in January 2026.

   
Left: New classroom walls going up at rear of sanctuary. Center: New restroom partitions in lower level. Right: Multi Purpose Room renovations underway.

Macedonia Missionary Baptist Church Celebrates Jubilee Opening

The Macedonia Missionary Baptist Church received its occupancy permit on November 12, 2025, just in time for the jubilee celebrating its re-opening! Click here for an article and additional photographs of the opening in the Ironton Tribune.

Left: Charissa Durst climbing into the attic during the final punch inspection on 11/7/2025. Center: Contractor Dan Mullins (left) and project manager Lacy Ward (right) with Charissa Durst on the church stoop after the punchlist. Right: Charissa Durst standing at the Jubilee celebration.  All photos by Jason Lucas.

Mount Zion Black Cultural Center Phase 1 Nears Completion

After a very wet spring and early summer, dry weather in late summer allowed Wolf Creek Construction to complete most of the exterior excavation and waterproofing, start the elevator addition, and pour the main basement floor slab. The floor is an 8” thick mat slab with 12” thick areas under future column locations. The floor is also heavily reinforced and attached to the exterior walls so rising water will not be able to dislodge it. One of the workers commented we could park an airplane in the basement! Wolf Creek Construction has also been awarded Phase 2 to rehabilitate the rest of the building, which will start once Phase 1 is closed out.
   
Left: View of the mud pit in the basement in April. Center: Rebar and vapor barrier being laid in preparation for the new concrete floor slab. Right: The new basement floor in September.

New Storage Building at Fernwood State Forest

The Fernwood State Forest storage building is almost complete, just waiting on final inspections and cleaning. The building has four storage bays with overhead doors, one of which has overhead doors on both the front and rear walls to allow vehicles to pull into the building to be loaded and unloaded out of the weather. On the east side of the building is a rainwater harvesting system that stores water from downspout runoff in an underground tank for washing vehicles outside. The Foresters should be able to start moving materials and equipment into the building in the next few months.
     
Exterior and interior views of the new storage building, which is almost complete.

Ohio’s First Black Church Nearing Renovation Completion

The Macedonia Missionary Baptist Church in South Point had some state grant money redirected to another project, so some items not essential to the occupancy permit had to be postponed. These included items such as the new wood floor, installing the original tin ceiling and the replacement pieces, new window and door casings, reinstalling the wood wall base, and interior painting. The exterior painted wood handicap ramp has also been swapped for a premanufactured aluminum ramp. The owners are hoping to raise enough private funds to finish the remaining work this year.
      
Left: View of the northeast corner of the church, which is still awaiting delivery of the new custom front doors. Right: Interior looking northwest toward the location of the new egress door, which will lead to the wheelchair ramp.

What Do We Do With All This Water?

When Intel decided to build a plant in Ohio, one of the reasons is the abundance of water. Apparently, data centers keep getting built here for the same reason. But it you are working on an old building with a basement, all that water can be a liability! At The Gardner House, Steller Construction finished installing the underpinning, new concrete slab floor, and exterior perimeter drain when a torrential downpour saturated the site. Rain came down so fast that the drainage system couldn’t get water out fast enough to prevent it from entering the basement. One solution is to add a drainage mat on top of the waterproofing to keep water off the exterior wall and direct it down to the drain pipe.
     
L: New fluid-applied waterproofing membrane that will be augmented with a drainage mat against the wall. R: An exiting cistern filled with water that we hope can be made into a historical exhibit that the pubic can view.
At Fernwood State Forest, the foundation drilling team working with E. Mullins Construction hit water that required the use of steel caissons to stabilize the shafts walls before the concrete could be poured. As an option, the driller could have eliminated caissons and used a slurry product known as “construction mud” (amongst other colorful names) in the shafts to keep the walls stable as concrete was being poured.
     
L: The Fernwood State Forest storage building in April 2025 with concrete piers curing in wood formwork. R: In July 2025, the floor slab in place and building framing up and anchored to pier foundations.
And finally, at Mount Zion Black Cultural Center in Athens, which is known to have a high water table, the constant rain made basement soil excavation a mud pit and caused the water table to rise. On the assumption that wet weather would only be more extreme in the future, HDC worked with the contractor Wolf Creek Contracting LLC  to raise the level of the basement floor and enclosed all sump pits in waterproofed concrete enclosures. The basement will still be usable space, but design changes eliminate floor finishes and keep drywall a few inches off the floor behind the vinyl baseboard to minimize water damage in the future.
     
L: Wolf Creek Contracting rigged up a conveyor system to remove mud and bricks from the basement. R: Water in the basement after another heavy rain slowed construction progress.

Northcoast Behavioral Health Starts Construction

After multiple years on hold for funding and more, the renovation of the Northcoast Behavioral Health Dietary Building started in June! The general contractor is Feghali Brothers LLC out of Canfield, Ohio. Initial work consists of interior demolition to remove built-in freezers and coolers, asbestos abatement, quarry tile removal, and some exterior siding/fascia removal. The finished project will provide additional office space, including a meeting room and break room, and expand the existing restrooms to accommodate additional office workers. The expanded restrooms will be fully accessible and one of the office workers will finally stop sharing space with the server/IT closet!

     
L: The floor under one of the removed coolers will be leveled and prepped to accept a new floor finish. R: Quarry tile marked for area to be removed.

Carol Stewart Village Starts Construction!

     
Left: View of west side looking north before construction. Right: View of west side looking south during construction with new curb and dog waste station.
HDC was commissioned by the City of Columbus to make improvements to Carol Stewart Village, a former 1980s hotel converted into housing for youths aged 18-24 who have aged out of the foster care system. Although the buildings had been renovated since the 1980s, the site around the building had not. HDC’s project includes the replacement of 70 packaged terminal air conditioners, or PTACs, ductless, self-contained air conditioning units that heat and cool small areas such as motel rooms and studio apartments. These units are also being anchored to prevent someone from breaking in from the outside. Sitework improvements include replacing crumbling concrete curbs and adding curbs where they do not exist now. The project also includes new dog waste disposal stations, which have already resulted in cleaner lawn areas. Another project repaved the parking lots. This project is just the beginning of improvements being made at Carol Stewart Village. Read about it in this Columbus Underground article.

HDC Welcomes Back Vivian Majtenyi!

The void left by the passing of Cathie Senter was thankfully filled by the return of Vivian Majtenyi in March. Vivian worked for HDC from 1999 (we were her first full-time architecture position) until 2013, when she left to take a break after working almost non-stop on our signature projects. During her 14 years at HDC, she traveled the country to complete facility assessments on Air Force Materiel Command installations and conduct research and documentation of historic buildings on navy bases. Vivian worked with Charissa Durst on the initial fieldwork at the Woodward Opera House through the rehabilitation of the second floor. She was also the project coordinator for both the addition to and renovation of the Lincoln Theatre and the addition and renovation of Stewart Elementary School. Vivian also obtained her architecture license in 2011. In the 10 years since she left HDC, her diverse work experience included the in-house design department of a construction firm, a large (over 650 employees) full-service A/E firm, and researching and writing historic architectural reports for cultural resources projects. Since HDC started new projects with the City of Columbus and State of Ohio this year, we are very happy to have Vivian back!
  
Left: Vivian leading a tour of the Lincoln Theatre. Right: Vivian’s celebratory cake upon passing the architecture license exam.